Indoor heated pool study out for comment

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

Community and stakeholder groups are being invited to provide comment on the recently completed needs assessment and feasibility study for an indoor heated swimming pool in Collie.

The study has identified a number of options, with varying costs and catering for different community needs.

Before making any decision, Council needs to understand which of the options caters for the greatest need, and how much capacity and appetite the community has to bear the ongoing costs of the project.

Community and stakeholder groups are being invited to provide comment on the recently completed needs assessment and feasibility study for an indoor heated swimming pool in Collie.

The study has identified a number of options, with varying costs and catering for different community needs.

Before making any decision, Council needs to understand which of the options caters for the greatest need, and how much capacity and appetite the community has to bear the ongoing costs of the project.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Please indicate your preferred option [Choose one only]

25m 6 lane pool Capital cost $4.8m; annual operating subsidy of $332,000, with an estimated impact on rates = 5.4% increase per annum or $68 per property.
34%
Indoor warm water pool Capital cost $2.2m; annual operating subsidy of $154,000, with an estimated impact on rates = 2.5% increase per annum or $31 per property.
9%
25m indoor 3 lane pool + program pool Capital cost $3.9m; annual operating subsidy of $268,000, with an estimated impact on rates = 4.4% increase or $55 per property.
15%
Do nothing. Continue to maintain and operate the pool as it is now [currently subsidised $484,000]
41%
Total Votes : 215